Vulcan Energy Resources Achieves Financial Close for Europe Project in June Quarter
MT Newswires Live
Jul 29
Vulcan Energy Resources (ASX:VUL) achieved financial close for its 2.2 billion euro phase one Project Lionheart in the Upper Rhine Valley Brine Field between Germany and France in the period ended June 30, according to a Wednesday filing with the Australian bourse.
The company also started civil construction activities at the Lionheart 30-megawatt geothermal power plant site in Germany, the filing said.
Bulk earthworks and the relocation of overhead high-voltage power lines are on track for completion by the third quarter, per the filing.
Shares rose 1% in morning trade Wednesday.
Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.